Title: RESOLUTION AUTHORIZING A SECOND NO COST TIME EXTENSION FOR THE COMMUNITY DEVELOPMENT BLOCK GRANT PROGRAM FY 2021 WEST MILFORD AMERICANS WITH DISABILITIES ACT BARRIER-FREE RAMP AT TOWNSHIP BUILDING #2 UNTIL FEBRUARY 28, 2025.
Attachments: 1. Cover Page, 2. RESOL ATTACHMENT - WEST MILFORD - 2nd NO COST EXTENTION 5.9.4

title

RESOLUTION AUTHORIZING A SECOND NO COST TIME EXTENSION FOR THE COMMUNITY DEVELOPMENT BLOCK GRANT PROGRAM FY 2021 WEST MILFORD AMERICANS WITH DISABILITIES ACT BARRIER-FREE RAMP AT TOWNSHIP BUILDING #2 UNTIL FEBRUARY 28, 2025.

 

body

WHEREAS, the Passaic County Board of County Commissioners (hereafter “Board”) adopted Resolution R-2018-0536 on June 26, 2018, authorizing the submission of a Five (5) Year Consolidated Plan for the period of FY 2018-2022 to the US Department of Housing and Urban Development (hereafter “USHUD”) in compliance with the Rules and Regulations governing the Community Development Block Grant Program (hereafter “CDBG”); and

 

WHEREAS, the Board adopted the FY 2021 Annual Action Plan via Resolution R-2021-0624 on June 22, 2021; and

 

WHEREAS, the Board is cognizant of the conditions imposed by the USHUD and included a grant allocation in the FY 2021 Annual Action Plan to the Township of West Milford (hereafter “Township”) for fifty thousand and 00/100 ($50,000.00) dollars to implement the Installation of an Americans with Disabilities Act Barrier-Free Ramp at Township Building #2; and

 

WHEREAS, the Township notified the Division of Economic Development that the Township (hereafter “Division”)  has been delayed in the implementation of the project due to the poor physical condition of Township Building #2 which must be excavated and restored to prevent water damage to the foundation of the building and requested that the CDBG FY 2021 grant award be extended for the first time to May 31, 2024 to permit the Township the time to complete the project; and

 

WHEREAS, the Board adopted Resolution R-23-0526 on May 23, 2023, providing a first no-cost time extension to May 31, 2024; and  

                       

WHEREAS, the Township has notified the Division, see attached correspondence, that the Township continues to be significantly delayed in the implementation of the project due to the poor physical condition of Township Building #2 which must be excavated and restored to prevent water damage to the foundation of the building and is requesting that the CDBG FY 2021 grant award be extended for the second time to February 28, 2025 to permit the Township the time to complete the project; and  

 

WHEREAS, this matter was discussed at the May 8, 2024, meeting of the County Commissioner Planning and Economic Development Committee and is being recommended to the Board for approval; and

 

WHEREAS, the Board considers this matter to be a benefit to the community and its residents;  

 

NOW, THEREFORE, LET IT BE RESOLVED, by the Board of County Commissioners of the County of Passaic, that it hereby authorizes the second no-cost time extension of the Community Development Block Grant Program FY 2021 grant to the Township of West Milford to February 28, 2025, as set forth above; and

 

LET IT BE FURTHER RESOLVED, that the County of Passaic Commissioner Director and Director of the Division of Economic Development are hereby authorized to act as the authorized representatives of the County to execute all necessary documents and certifications on behalf of the County of Passaic.

 