RESOLUTION AUTHORIZING CONTRACT MODIFICATION NO. 1 TO PENNONI ASSOCIATES, INC. FOR ASBESTOS ABATEMENT CONSULTANT SERVICES AT 11 EDGAR DRIVE IN THE TOWNSHIP OF WEST MILFORD, RFQ-24-043, PURSUANT TO N.J.A.C. 5:30-11.6.
body
WHEREAS, the County of Passaic (hereafter “County”) is a body politic and corporate pursuant to N.J.S.A. 40:18-1 and vested with all rights contained therein; and
WHEREAS, pursuant to N.J.S.A. 40:20-1 the Board of County Commissioners of the County of Passaic (hereafter “Board”) is vested with managing the property, finances, and affairs of the County; and
WHEREAS, pursuant to N.J.S.A. 40A:11-5, et seq. the County issued RFQ-24-043, Engineers, Architects, Land Surveyors, Planners, Landscape Architects, Golf Course Architects/Designers, And Environmental and Safety/Engineering Consultants (hereafter “RFQ-24-043”) seeking qualifications for a pool of engineers, architects, land surveyors, planners, landscape architects, and environmental health and safety engineers for calendar year 2024, to be hired on an as-needed basis, to provide professional services to the County; and
WHEREAS, on November 21, 2023, the Board passed Resolution No. R-23-1091, qualifying a pool of engineers, architects, land surveyors, planners, landscape architects, and environmental health and safety engineers for calendar year 2024, as recommended by the Passaic County Engineer, to be hired on an as-needed basis, which included Pennoni Associates, Inc.; and
WHEREAS, pursuant to N.J.S.A. 19:44A-20.4, the County’s request for qualifications is a fair and open process, specifically, the qualification for the pool of engineers, architects, land surveyors, planners, landscape architects, and environmental health and safety engineers for calendar year 2024 is publicly advertised, awarded under a process that provides for public solicitation of qualifications, established the basis of an award and disclosure process documented in writing prior to any solicitation, and is publicly opened and announced when awarded; and
WHEREAS, on September 10, 2024, the Board passed Resolution No. R-24-780, authorizing an award of contract to Pennoni Associates, Inc., to provide asbestos abatement services during the asbestos phase at the Passaic County Health Department Satellite Office at 11 Edgar Drive in the Township of West Milford in an amount not to exceed nine thousand seven hundred dollars ($9,700.00); and
WHEREAS, pursuant to N.J.A.C. 5:30-11.6, the County can authorize contract modifications for professional services and extraordinary unspecifiable services, when the change is outside the original scope of activities of the original contract, provided that any change beyond the original scope of activities shall be made by amendatory contract approved by the governing body; and
WHEREAS, the Passaic County Engineer is recommending that the Board authorize Contract Modification No. 1 to Pennoni Associates, Inc., to cover for a Subchapter 8 Oversite and the Generation of a Technical Specification which was not included in the original contract, in the increased amount of ten thousand eighty-eight dollars ($10,088.00), with a new total contract amount, as a result of the increase, in the amount of nineteen thousand seven hundred eighty-eight dollars ($19,788); and
WHEREAS, funds are available in Account No., C-04-55-175-001-901 or any other account that may be deemed appropriate by the Chief Financial Officer or his designee, and the availability of funds has been contingently certified by the Chief Financial Officer subject to sufficient funds being appropriated by the Board in the 2024 and/or subsequent years’ County budget(s), which is attached to and made part of this Resolution; and
WHEREAS, this matter was discussed with the Public Works Committee on December 11, 2024, and is being recommended for approval.
NOW, THEREFORE, LET IT BE RESOLVED, pursuant to N.J.A.C. 5:30-11.6, that the Board of County Commissioners of the County of Passaic hereby authorizes Contract Modification No. 1 to Pennoni Associates, Inc., to cover for a Subchapter 8 Oversite and the Generation of a Technical Specification which was not included in the original contract, in the increased amount of ten thousand eighty-eight dollars ($10,088.00), with a new total contract amount, as a result of the increase, in the amount of nineteen thousand seven hundred eighty-eight dollars ($19,788), as recommended by the County Engineer.
LET IT BE FURTHER RESOLVED, the Clerk to the Board shall print, in the official newspaper, a brief notice stating the nature, duration, service, and amount of the contract to Pennoni Associates, Inc. and maintain a copy of the resolution on file and available for public inspection in the Office of the Clerk to the Board.
LET IT BE FURTHER RESOLVED, that the Clerk of the Board, County Counsel, and Director of the Board of County Commissioners are authorized to execute the contract and take any other steps necessary to carry out the purpose of this Resolution.
ZMQ December 30, 2024