Title: RESOLUTION AUTHORIZING CHANGE ORDER NO. 8 FOR CAP ELEVATOR, LLC, FOR THE ELEVATOR MODERNIZATION AND REHABILITATION PROJECT AT PREAKNESS HEALTHCARE CENTER, PER BID C-23-001, PURSUANT TO N.J.A.C. 5:30-11.3 ET SEQ.
Attachments: 1. Cover Page, 2. 26-0788, 3. June 11, 2026 County Administrator Memorandum_Final Change Order (CAP Elevator, LLC), 4. 20% Change Order_Preakness Healthcare Elevators_CAP Certification

title

RESOLUTION AUTHORIZING CHANGE ORDER NO. 8 FOR CAP ELEVATOR, LLC, FOR THE ELEVATOR MODERNIZATION AND REHABILITATION PROJECT AT PREAKNESS HEALTHCARE CENTER, PER BID C-23-001, PURSUANT TO N.J.A.C. 5:30-11.3 ET SEQ.

 

body

                     WHEREAS, the County of Passaic (hereafter “County”) is a body politic and corporate pursuant to N.J.S.A. 40:18-1 and vested with all rights contained therein; and

 

WHEREAS, pursuant to N.J.S.A. 40:20-1 the Board of County Commissioners of the County of Passaic (hereafter “Board”) is vested with managing the property, finances, and affairs of the County; and

 

                     WHEREAS, pursuant to N.J.S.A. 40A:11-4, et seq., every contract awarded by the County, for the provision or performance of any goods or services, the cost of which in the aggregate exceeds the bid threshold [40A:11-3], shall be awarded only by resolution of the Board to the lowest responsible bidder after public advertising for bids and bidding thereof; and

 

WHEREAS, on February 22, 2023, the Purchasing Agent issued C-23-001, Elevator Modernization, and Rehabilitation at Preakness Healthcare Center (hereafter “C-23-001”) seeking sealed proposals from qualified bidders for the Elevator Modernization Project at Preakness Healthcare Center; and

 

WHEREAS, on April 11, 2023, the Board passed Resolution No. R-23-0372 authorizing an award of contract to CAP Elevator, LLC, the lowest responsible bidder under C-23-001, in an amount not to exceed two million two hundred fifty-five thousand dollars ($2,255,000.00).; and

 

WHEREAS, pursuant to N.J.A.C. 5:30-11.3, et seq. the Board can authorize, permit, or accept change orders for work performed, services rendered, materials, supplies, or equipment delivered or provided pursuant to the conditions as set forth therein; and

 

WHEREAS, in compliance with N.J.A.C. 5:30-11.3 et seq., the Board has approved the following change orders for the Project to date:

 

CHANGE ORDER

AMOUNT

ADJUSTED CONTRACT

RESOLUTION

Change Order No. 1

$29,600

$2,284,600.00

R-23-0953

Change Order No. 2

$135,380.00

$2,419,980.00

R-23-1239

Change Order No. 3

$29,750.00

$2,449,730.00

R-24-0945

Change Order No. 4

$187,860.00

$2,637,590.00

R-25-0445

Change Order No. 5

$37,100.00

$2,674,690.00

R-25-0505

Change Order No. 6

$18,300.00

$2,692,990.00

R-25-845

Change Order No. 7

$4,800.00

$2,697,790.00

R-25-1033

 

WHEREAS, the Passaic County Engineer is recommending that Change Order No. 8 be authorized for a net addition in the amount of fifty five thousand seven hundred fifteen dollars ($55,715.00) to address unforeseen conditions, with a new total contract award, as a result of the increase, in the amount of two million seven hundred fifty three thousand five hundred five dollars ($2,753,505.00); and

 

WHEREAS, this proposed Change Order No. 8 will result in the net sum of change orders for this project to be in excess of the 20% limit for change orders which is permitted pursuant to N.J.A.C. 5:30-11.3 et seq.; and

 

WHEREAS, pursuant to N.J.A.C. 5:30-11.9 change orders in excess of 20% are permitted as long as the following is present:                     

1)                     a written certification by the contractor containing the following:

 

i)                     an explanation of the factual circumstances which necessitate issuance of the change order;

ii)                     a statement indicating why these circumstances could not have been foreseen;

iii)                     a statement indicating why issuance of the change order would be in the best interests of the County and would not constitute an abuse of these rules;

iv)                     if the nature of the change order is technical, the certification shall include a certified statement from contractor’s appropriate expert, explaining in detail the factual circumstances which necessitate the issuance of the change order;

 

2)                     a request from the chief executive officer, in this case the County Administrator, or his designee, to the governing body requesting the change order and explaining why this change order may be allowed pursuant to this provision

 

WHEREAS, the CEO of CAP Elevator Inc., submitted a letter to the County Administrator dated  June 4, 2026 requesting the adoption of Change Order No. 8, copies of which are attached hereto and made a part hereof; and

 

WHEREAS, the Passaic County Administrator has filed a letter with the Board dated June 11, 2026 requesting that the Board review this matter and consider adopting this Change Order a copy of which is attached hereto and made a part hereof; and

 

WHEREAS, funds are available in Account No. C-04-55-176-002-920, or any other account that may be deemed appropriate by the Chief Financial Officer or his designee, and the availability of funds has been contingently certified by the Chief Financial Officer subject to sufficient funds being appropriated by the Board in the 2026 and/or subsequent years’ County budget(s), which is attached to and made part of this Resolution; and

 

                     WHEREAS, this matter was discussed at the May 27, 2026 meeting of the Public Works Committee, and is being recommended to the Board for approval.

 

NOW, THEREFORE, LET IT BE RESOLVED, pursuant to N.J.A.C. 5:30-11.3, et seq., the Board of County Commissioners of the County of Passaic authorize Change Order No. 8 for the contract with CAP Elevator, LLC, under C-23-001, in the increased amount of fifty five thousand seven hundred fifteen dollars ($55,715.00), with a new total contract award, as a result of the increase, in the amount of two million seven hundred fifty three thousand five hundred five dollars ($2,753,505.00).

 

LET IT BE FURTHER RESOLVED, that in accordance with N.J.A.C. 5:30-11.9, the Board of County Commissioners of the County of Passaic authorizes a written amendatory contract covering the changes to the project described herein.

 

LET IT BE FURTHER RESOLVED, the Clerk to the Board shall publish on the Public Notices page of the County’s website, a brief notice stating the additional amount to be expended, the original contract price, the nature of the original and additional work authorized by the within resolution and why it is necessary to expend the additional funds and maintain a copy of the resolution on file and available for public inspection in the Office of the Clerk of the Board.

 

LET IT BE FURTHER RESOLVED, that the County Engineer is authorized and directed to comply with all of the general requirements for change orders as set forth in N.J.A.C. 5:30-11.3, et seq.

                     LET IT BE FURTHER RESOLVED, that the Clerk of the Board, County Counsel, County Engineer, and Director of Board of County Commissioners are authorized to take any other action necessary to carry out the purpose of this Resolution. 

 

ZMQ                                                                                                                                                                                                                           August 11, 2026