File #: 26-0406   
Type: Resolution Status: Passed
File created: 4/29/2026 In control: Public Works
On agenda: 5/12/2026 Final action: 5/12/2026
Enactment date: 5/12/2026 Enactment #: R-26-0404
Title: RESOLUTION AUTHORIZING CHANGE ORDER NO. 3 FOR NEW PRINCE CONCRETE CONSTRUCTION COMPANY, INC. FOR THE OLDHAM ROAD (C.R. 685) IMPROVEMENTS FROM PREAKNESS AVENUE (C.R. 666) TO PATERSON HAMBURG TURNPIKE/CENTRAL AVENUE (C.R. 673), PER BID C-25-004, N.J.A.C. 5:30-11.3 ET SEQ.
Attachments: 1. Cover Page, 2. NEW PRINCE - OLDHAM RD (CR 685) IMPROVEMENTS PREAKNESS TO PATERSON AVE

title

RESOLUTION AUTHORIZING CHANGE ORDER NO. 3 FOR NEW PRINCE CONCRETE CONSTRUCTION COMPANY, INC. FOR THE OLDHAM ROAD (C.R. 685) IMPROVEMENTS FROM PREAKNESS AVENUE (C.R. 666) TO PATERSON HAMBURG TURNPIKE/CENTRAL AVENUE (C.R. 673), PER BID C-25-004, N.J.A.C. 5:30-11.3 ET SEQ.

 

body

WHEREAS, the County of Passaic (hereafter “County”) is a body politic and corporate pursuant to N.J.S.A. 40:18-1 and vested with all rights contained therein; and

 

WHEREAS, pursuant to N.J.S.A. 40:20-1 the Board of County Commissioners of the County of Passaic (hereafter “Board”) is vested with managing the property, finances, and affairs of the County; and

 

WHEREAS, pursuant to N.J.S.A. 40A:11-4, et seq., every contract awarded by the County, for the provision or performance of any goods or services, the cost of which in the aggregate exceeds the bid threshold, shall be awarded only by resolution of the Board to the lowest responsible bidder after public advertising for bids and bidding thereof; and

 

WHEREAS, on January 24, 2025 the Purchasing Agent issued Oldham Road (C.R. 685) Improvements from Preakness Avenue (C.R. 666) To Paterson Hamburg Turnpike/Central Avenue (C.R. 673), Bid No. C-25-004 (hereafter “C-25-004”) seeking sealed proposals from qualified bidders to construct various improvements along the entirety of Oldham Road, and portions of Preakness Avenue and Paterson-Hamburg Turnpike/Central Avenue in the Township of Wayne; and

 

WHEREAS, on March 25, 2025, the Board passed R-25-268 authorizing an award of contract to New Prince Concrete Construction Company, Inc., the lowest responsible bidder under C-25-004, in an amount not to exceed twelve million seven hundred ninety-eight thousand eight hundred forty-five dollars and fifteen cents ($12,798,845.15); and

 

WHEREAS, pursuant to N.J.A.C. 5:30-11.3, et seq., the Board can authorize, permit, or accept change orders for work performed, services rendered, materials, supplies, or equipment delivered or provided pursuant to the conditions as set forth therein; and

 

WHEREAS, the Board has approved the following change orders for the project under C-25-004 to date:

 

Change Order

Amount

Adjusted Contract Total

Resolution

Change Order No. 1

$30,451.80

$12,829,296.95

R-25-1105

Change Order No. 2

$308,719.49

$13,138,016.44

R-26-0072

 

WHEREAS, the Passaic County Engineer is recommending that Change Order No. 3 be authorized for a net deduction to the contract under C-25-004 in the amount of eleven dollars and ninety-five cents ($11.95) due to field quantity adjustments needed to complete this project, with a new total contract amount of thirteen million one hundred thirty-eight thousand four dollars and forty-nine cents ($13,138,004.49); and

 

WHEREAS, this project is being funded through County Aid Grants from the New Jersey Department of Transportation; and

 

WHEREAS, this matter was discussed at the April 29, 2026, meeting of the Public Works Committee and is being recommended to the Board for approval; and

 

NOW, THEREFORE, LET IT BE RESOLVED, pursuant to N.J.A.C. 5:30-11.3, et seq., that the Passaic County Board of County Commissioners hereby authorizes Change Order No. 3 and Final to New Prince Concrete Construction Company, Inc. for the Oldham Road Improvements Project, in the Township of Wayne, in the decreased amount of eleven dollars and ninety-five cents ($11.95), with a new total contract amount, as a result of the decrease, of thirteen million one hundred thirty-eight thousand four dollars and forty-nine cents ($13,138,004.49).

 

LET IT BE FURTHER RESOLVED, that the County Engineer is authorized and directed to comply with all of the general requirements for change orders as set forth in N.J.A.C. 5:30-11.3, et seq.

 

LET IT BE FURTHER RESOLVED, that the Clerk of the Board, County Counsel, County Engineer, and Director of Board of County Commissioners are authorized to take any other action necessary to carry out the purpose of this Resolution and to execute any supporting documents required for grant reimbursement.

 